Ballast deliveries

DATE POSTED: 13 Jul 2024

Last Wednesday more profile boards were set up to the left hand side of the trackbed (looking North): this will make it easier to level the ballast. Today a further 20 tonnes of 6F2 fill were delivered to build up the levels from ch170 to ch230 and rolled. This was followed by a further 20 tonnes of ballast.